Nottinghamshire Highways Partnership
A Project that has required integration of people, practices and cultures from the public and private sectors. NHP is a collaborative contract delivering highway maintenance and improvement works throughout the county. The Partnership benefits from co-ordinated programming of schemes, accurate long term budget forecasting and efficient use of resources.
Completing much more than surfacing through the Area 7 MAC
As one of AMScott's first tier supply chain partners, Tarmac undertakes all aspects of motorway and trunk road maintenance work across Area 7. Tarmac is involved with each initial scheme design, production of budget costs, joint walk through inspections, the procurement of a supply chain, programming, managing and supervising the works and the preparation of hand-over documents.
A52 Holme House to RSPCA, Nottinghamshire
Tarmac was required to re-surface 400m of both carriageways of the dual A52 in Gamston. The scheme design had identified a 180mm layer of tarbound material that would cost £110 per tonne to safely dispose of. Based on advice given by Tarmac's in-house technical team, it was agreed to excavate, recycle and re-use the material as a lower layer FoamMaster base.
Design and Build - RAF Lakenheath, In-Transit Platform
A Design and Construct contract to provide parking facilities for heavy freight aircraft such as the C-5 Galaxy and Boeing C-17 Globemaster.
Liverpool John Lennon Airport Runway Strengthening
Working five or six nights a week, possession of the runway commenced at 23.30hrs with cold milling, by NRP. Upon completion, at approximately 01.00 hrs, laying commenced with three paving machines laying in echelon formation. The runway had to be handed back by 06.00hrs and therefore surfacing was programmed to be complete by 04.30hrs.
Renfrewshire Council - Structural Maintenance Contract 2006 - 2009 (Phase 1 and Phase 2)
The Project Brief was to work in partnership with Renfrewshire Council to provide optimum levels of highway maintenance and upgrade work.
Carriageway Widening at Moulton Paddocks Estate
Widening of existing B1506 Bury Lane, over 285 m, to give 3 No. 3.5m traffic lanes and 1m hardshoulder, providing a filter lane for the entrance to Moulton Paddocks Estate. The width of the widening varied from zero to 4.5m.
Norwich Airport - Runway Rehabilitation Works
This work had to be completed using weekend restrictions to the runway. Tarmac were asked to excavate and dispose on site, the existing concrete construction of Taxiway Charlie and replace with 200mm wet lean and 350mm PQ Concrete and install new taxiway surface markings.
EME2 on the M9 / A90 Spur
Tarmac were the specialist subcontractor awarded a £6.2m contract by Morrison Construction to undertake all surfacing works on the M9 / A90 Spur. Almost 200,000 tonnes of asphalt were laid over a 12 month period that included 27,300 tonnes of high strength, long life EME2 along heavily laden sections of the A90.
Scottish Motorway and Trunk Road Refurbishment and Reconstruction
Tarmac has been maintaining Transport Scotland's (and its predecessor, the Scottish Executive) road network for over 50 years. We have successfully undertaken contracts on almost all motorways and trunk roads from the Scottish Borders to the Highlands gaining an invaluable knowledge that is taken forward by a dedicated team of site management onto the next site and the next contract.
Urban Vision Partnership Ltd - Rethinking Construction in Salford
Tarmac work alongside Urban Vision Partnership (Salford City Council, Capita Symonds and Morrison Construction) and Birse to deliver Salford City Council's Highways and Civil Engineering capital works programme.
Forth Estuary Transport Authority (FETA)
FETA's Project Brief was to avoid carriageway occupation during weekdays and the peak holiday period. To maintain flows of weekday traffic the Works had to be completed in two phases during a series of weekend carriageway possessions.
Possessions were not permitted during the peak holiday period and therefore Phase 1 was completed between April and June with Phase 2 completed during September and October.
A1094 Aldeburgh Road Reconstruction, Suffolk
Suffolk County Council has traditionally used hot-rolled asphalt for re-surfacing their roads across the County. However, to assist with the County's ambition of being one of the greenest in the country, the A1094 was identified as a suitable location to trial the use of FoamMaster.
A477 Kilgetty Bypass - Stepaside Junction
The contract required Tarmac to reconstruct and resurface 5.6km of the A477 in South Carmarthenshire using ex-situ recycling techniques.
Donington Park - Track Resurfacing and
Redevelopment of Old Hairpin
Read about the resurfacing of Donington Park's 4km circuit, including new kerbing, a gravel trap run-off at the Old Hairpin, improved pit-lane access and white lining.
Newcastle International Airport - North Apron Extension
In order to enlarge the existing North Apron a previously undeveloped, greenfield area of the site was excavated to an average depth of 1250mm. This required the removal of existing lighting columns (and their reinforced bases), AGL lighting and associated cabling.
Newcastle International Airport Limited Winter Upgrade
Upgrade of existing paved areas within the confines of the busy Newcastle working airport environment, over a winter nightime, five month project.
Multi Use Games Area (MUGA) at Emmanuel College, Gateshead
Following site preparation work, a 300mm thick layer of Type 3 reduced fines Granular Sub base was laid, with the final 50mm laid using the Lazerpave system. This layer provided the platform for the permeable asphalt layers and allowed drainage of water through to the subsoil.
London City Airport - Western Apron Extension
Project aims was to construct three additional Aircraft Stands on the Western Apron at London City Airport. The project required partial demolition of the old Ground Services building and extension of the existing perimeter security fence to enclose the redundant Old Hartman Road access, and thus provide the extra footprint for the new stands to be constructed.
A21 / A2100 Johns Cross Junction Improvement
Tarmac was required to re-model a complex and unorthodox series of give-way junctions into a roundabout. In order to facilitate the new horizontal alignment of this roundabout a length of the A21 Trunk Road required realignment.
.


