Forth Estuary
Forth Estuary Transport Authority (FETA)
Contract detail: Northbound Carriageway (completed Oct 2007)
Value: £4m
Duration: 18 weekends in two work phases
Southbound Carriageway (completed Oct 2004)
Value: £3.24m
Duration: 18 weekends in two work phases
FETA's Project Brief was to avoid carriageway occupation during weekdays and the peak holiday period. To maintain flows of weekday traffic the Works had to be completed in two phases during a series of weekend carriageway possessions.
Possessions were not permitted during the peak holiday period and therefore Phase 1 was completed between April and June with Phase 2 completed during September and October. The Contract required the removal of the bridge deck's surfacing and waterproofing. Any identified remedial works were then undertaken to the steel and concrete decks prior to the application of new spray applied waterproofing membrane and hand laid mastic asphalt surfacing impregnated with pre-coated chippings.
Download: Forth Bridge Road (pdf, 390kb)
See more on Asphalt Surfacing
Why Tarmac National Contracting?
- National coverage - local service
- Clear focus on teamwork, innovation and safety, underpinned by our Sustainability framework.
- Close client collaboration to help support new regulations and the complex demands for highways maintenance.
- Played a major role in developing, modernising and maintaining the UK roads and transport infrastructure.
- Our extensive experience enables us to utilise our skill and versatility to benefit a variety of customers and sectors.
- Building relationships to deliver with a range of local authorities.
- Highly qualified teams providing a range of services and innovative products.
See more in About National Contracting
Product and technical specification downloads
Find out more...
Case study downloads