Toproc, Topforce and Toptint at Blackpool sea defence
- Blackpool’s biggest ever civil engineering project involved the replacement and reconstruction of 3.2 km of promenade and sea defence walls.
- Constant bombardment from winter storms for over 100 years had taken its toll on the sea wall and a 5 year project was undertaken to rebuild both the sea walls and the promenade.
- Tarmac worked very closely with Blackpool Borough Council and Birse Coastal to provide a variety of concretes that satisfied many operational requirements.
Tarmac's solution
The contract was both architecturally and aesthetically demanding and required precision working within the narrow tidal windows available. A working window of just six to eight hours a day meant Tarmac had to consistently deliver the right quality at the right time. A dedicated batching plant and expert technical support helped it pull off the feat.
Overall Tarmac supplied over 45,600m3 of concrete, 27,600m3 of Topforce reinforced concrete, 24,000m3 of Toptint coloured concrete and 6,700m3 of Toproc high performance concrete to the project.
See more on:
Why Tarmac Toproc high performance concrete?
- BBA-certified
- Longer lasting than conventional concrete
- Reduce costs over their longer lifetimes
Why Topforce reinforced concrete
- No need for stock piles of steel fabric on-site
- No need for placing steel fabric
- Long lasting
- Easy to lay
Why Toptint coloured concrete?
- Coloured concrete available in a range of colours
- Colour consistency from batch to batch
- Enhanced design and flexibility