Jump to content

A52 Holme House to RSPCA, Nottinghamshire

A52 Holme House to RSPCA, Nottinghamshire



Client: Highways Agency / AmScott (MAC7)
Value: £1.2 million
Duration: 9 weeks
Completion: December 2007

A ProjectBrief included a requirement to remove bound material containing tar. Tarmac suggested this be processed into cold lay FoamMaster and enabled the client to save over £125,000 in disposal costs..

Tarmac was required to re-surface 400m of both carriageways of the dual A52 in Gamston. The scheme
design had identified a 180mm layer of tarbound material that would cost £110 per tonne to safely dispose of.  Based on advice given by Tarmac's in-house technical team, it was agreed to excavate, recycle and re-use the material as a lower layer FoamMaster base..

Tarmac have been assisting with MAC 7 scheme designs 2002
Tarmac has been undertaking over 50 schemes per annum on behalf of AmScott, the Highways Agency's
MAC Operator, since their initial award of the contract in July 2002. At an early stage of each Works Order
we are involved in the scheme design and responsible for procuring the requisite supply chain to ensure
a best value package is agreed.


Comment:
"Using FoamMaster means fewer lorry movements, so the job is completed quicker, with less disruption
to local residents and motorists. It also saves material ending up in landfill sites, saving money and helping the environment."
Andy Butler Schemes Manager, AmScott

As a specialist supply chain partner, Tarmac supply and lay all surfacing work up to a value of £500,000, with schemes ranging from footpath surfacing to bridge deck re-waterproofing and night time remedial works on the M1 motorway. Other in-house capabilities that are regularly used include cold milling (NRP) safety fencing and electrical works. Tarmac's contract is worth £4m per annum and is
due for completion in June 2009.


Such is AmScott's confidence in Tarmac's abilities that this particular scheme involved three separate Works Orders issued in tandem, with initial discussions having being held some eight weeks prior to start of the scheme.


5,000 miles of transport movements and 100 tonnes of CO2 emissions were saved by using FoamMaster


NRP removed 5,820 tonnes of the existing carriageway surfacing by cold milling to a depth of 380mm with all arisings taken to Hoveringham Quarry, less than 18km from site.  Arisings from the lower 180 mm comprised tarbound material (1,160 tonnes) that were stored separately from the other planings on an impervious (concrete) surface and kept sheeted.


100% of the tarbound arisings were crushed, screened and graded prior to mixing and processing into FoamMaster.  By adding in a percentage of the other planings a total of 2,316 tonnes of FoamMaster, at a depth of 280mm, was relaid in three equal layers.

FoamMaster

Tarmac's cold lay FoamMaster product is essentially 88% highway arisings, 7% pulverised fuel ash,
2% cement and 3% bitumen, with an addition of water to meet the optimum water content target.  This system's primary advantages over conventional surfacing techniques are that it is an energy efficient
manufacturing process that reduces site transport movements and conserves local aggregate resources.

Strict testing regime ensured a Quality Product
As part of Tarmac's quality assurance, the recycled mix was tested to ensure it met the performance requirement for stiffness and standards specified in TRL 611, 2004, which provides a guide to the use and specification of cold lay recycled materials.

Comment:
"Excellent site staff with excellent backup from commercial team. Good use of quality supply chain"
Richard Acklam Project Manager, AmScott

Successful recent experience of tarbound materials was a factor in promoting the scheme

70,000 tonnes of carriageway arisings were recycled into FoamMaster during the A38 Peartree to Drybridge renewal scheme in Devon, which Tarmac completed in March 2006 on behalf of the Highways Agency (HA). This included 5,816 tonnes of Tarbound material that was discovered after works had started. Having gained both Environment Agency and HA approval the material was planed out and then incorporated and encapsulated back into the permanent works (in the same 2km stretch from which it was removed), thus saving approx. £400,000 of tipping costs at Swindon, the nearest licenced tip,
over 140 miles away.


Tarbound carriageway planings have also been incorporated into FoamMaster on the A38 Trerulefoot in Cornwall (6,882 tonnes, Jan/Feb 2007) and on side roads during the widening of the M1, Junction 6A to 10 (560 tonnes, Oct. 2007).  In both instances this option was chosen to prevent the materials
going to landfill.

 

Download:

A52 Holme House (pdf, 308kb)

See all National Contracting services offered for the Highways sector.

Back to National Contracting Home



Back to top