Donington Park - Track Resurfacing and Redevelopment of Old Hairpin
Client: Clear Channel Entertainment
Value: £ 900,000
Duration: 14 weeks
Completion: February 2004
Project Brief
To completely resurface Donington Park's 4km circuit, including
new kerbing, a gravel trap run-off at the Old Hairpin, improved
pit-lane access and white lining.
Background to the Contract
After meeting the rigorous demands of a
spectrum of motorsport events (from the British
Motorcycle Grand Prix and the British Touring
Car Championship to the British Superbikes) the
track had become uneven and was unable to
meet the stringent requirements of Donington
Park and its consulting engineers.
In addition to the fact that the skid resistance
value of the old surface had fallen below minimum requirements, overall ride-ability needed to be improved, additional run-off at
the Old Hairpin was required, as well as better access
between the pit-lane and track for starting wheels. With challenging weather conditions, and a whole
season of prestigious motorsport events ahead, it was
critical that the contract was finished within the set time
scale.
The Technical Challenge
The Donington Park contract was divided into 2 main parts:
the redevelopment of Old Hairpin (included extending the
gravel trap by 15metres; relocating adjacent tyre barriers,
safety fencing, retaining wall, Marshall post and access gates;
demolishing an existing toilet facility; landscaping the
spectator area embankment and constructing a new foul
sewage pumping station) and secondly the resurfacing of the
circuit and included the full-width reconstruction of 30metres
of track between Coppice Corner and McLeans; surfacing of
an infield access track using 100mm of compacted planings
from the old track surface; surfacing the pre-trial in the
Paddock; and resurfacing the full Grand Prix Loop.
The Surfacing Solution
The new track surface was laid at 40mm thick using Delugrip RSM, chosen for its ability to provide a dense, impermeable and deformation-resistant surface with a macrotexture designed to assist bulk surface water run-off. Delugrip RSM uses a combination of aggregates with different wear characteristics which effectively help to maintain macrotexture and maximise skid resistance in all conditions. In order to ensure smoothness and minimise joints Tarmac employed four pavers (two in echelon with one on stand-by) and a mini-paver for those areas where the circuit widened. The pavers were supported by four larger tandem rollers, one small tandem and two deadweight rollers, and the joints were located off the racing lines and braking zones. Compliance checks were carried out during laying, using the TRL pendulum skid meter, as well as transverse and rolling straight edges - with a 3mm tolerance throughout.
Materials
The resurfacing contract generated over 5,000 tonnes of
planings, a portion of which was subsequently recycled and
reused in the reconstruction of the infield access. Resurfacing
the 4km of track required 4,850 tonnes of asphalt and 8km of
white lining. The extensions to the gravel trap required 3,400
tonnes of gravel.
"The track was really rippled before and you had to think about
what line to take to avoid the bumps, but now its completely
smooth. The surface is consistent now and that's important to
me because I race here regularly. My prediction for this new
track is that it should shave off one second [from the lap time]
easily -well that's what I'm hoping for!"
Matt Llewellyn
Ducati British Superbike Rider - Lloyds Racing
Download:
See more on National Road Planing
See all National Contracting Products and Services
Back to National Contracting Home



